How long will it take to rebuild Blue Origin's launch pad? We asked some SpaceX vets.
Ars Technica ·

The closest analog to what Blue Origin is attempting to do, therefore, concerns the rebuild of Space Launch Complex-40, which was largely destroyed by the AMOS-6 failure. …
The closest analog to what Blue Origin is attempting to do, therefore, concerns the rebuild of Space Launch Complex-40, which was largely destroyed by the AMOS-6 failure. According to Muratore, SpaceX was not allowed to begin reconstruction work at the launch pad until January 2017. The delay stemmed from the ongoing investigation, which included a grid-by-grid examination of debris, cataloging recovered materials, and launch site remediation. Muratore and other SpaceX engineers spent these four months redesigning the launch pad. SpaceX’s Falcon 9 rocket and Cargo Dragon spacecraft, seen here with the new launch tower and access arm at SLC-40. Credit:
SpaceX SpaceX’s Falcon 9 rocket and Cargo Dragon spacecraft, seen here with the new launch tower and access arm at SLC-40. Credit:
SpaceX Trip Harriss, who managed the Falcon 9 fleet operations in 2016, said everyone at the company pitched in to support the investigation and then the reconstruction of the SLC-40 pad. The search for debris lasted from shortly after the explosion until early October, when efforts had to be abandoned due to the approach of the powerful Hurricane Matthew. During this time, SpaceX pulled out all of the stops, deploying drones and aircraft with sensitive equipment. “At one point, I got a submersible to take into the flame trench, where there was an accumulation of water, to see if we could find any rocket debris,” Harriss said. …
Original source: Ars Technica